§ 21-168. Scope.  


Latest version.
  • Pursuant to this division, all sites where crushing operations are performed are required to obtain a permit. Existing operations, expansions of existing operations and new operations are required to follow the permit application procedures in section 21-171 of this Code. Expansions of existing operations and new operations shall meet the location requirements in section 21-170 of this Code. However, the location requirements in section 21-170, notice requirements set forth in section 21-174 and the hearing and appeal procedures set forth in section 21-175, all sections of this Code, shall not apply to existing operations or to temporary crushing operations located at demolition sites if the concrete is being crushed primarily for use at the demolition site.

(Ord. No. 07-545, § 2, 5-9-07)