§ 40-121. Definitions.  


Latest version.
  • As used in this article, the following terms shall have the meanings ascribed in this section, unless the context of their usage clearly indicates another meaning:

    Applicant means any person who seeks a permit for an excavation.

    Backfill means excavation fill material meeting city specified quality requirements or the placement thereof.

    Construction standards means the City of Houston Standard Specifications for Wastewater Collection Systems, Water Lines, Storm Drainage, and Street Paving and the City of Houston Standard Construction Details for Wastewater Collection Systems, Water Lines, Storm Drainage, and Street Paving as they may be amended from time to time by Houston Public Works and approved by the city engineer.

    Emergency means an unforeseeable event or occurrence that endangers health, life, or property, or a situation in which public need for uninterrupted utility service requires immediate corrective action to restore services.

    Excavation means an activity that cuts, penetrates, or bores under any portion of the public way that has been improved with a paved surface for street, sidewalk, surface drainage, or related public transportation infrastructure purposes. The term includes but is not limited to cutting, tunneling, jacking and boring, backfilling, restoring, repairing, and installing and maintaining a temporary surface in, the public way. The term does not include a transportation improvement; however, it does include excavations that are undertaken for the improvement or maintenance of publicly owned utility systems, such as water and wastewater lines and facilities. The term also does not include utility maintenance or other activities that are performed within already existing structures, vaults, conduits, or cable ways that are located underneath street improvements, provided that any access required for the work is obtained through manholes, or other previously constructed entrances that may be utilized without cutting or penetrating any pavement or other street improvement.

    Facility means any structure, device, or other thing whatsoever that may be installed or maintained in, on, within, under, over, or above a public way by an excavation.

    Inspection means the inspection of an excavation by any person approved by the city engineer to determine compliance with this article.

    Owner means a person, including the city, who is the owner or will, following the completion of the installation, become the owner of any facility that is installed or is proposed to be installed or maintained in the public way.

    Permit means a current and valid authorization issued under division 2 of this article.

    Permittee means a person who holds a permit; the singular term includes the plural if two or more persons jointly hold the permit, where applicable.

    Public way means any public street right-of-way located in the city, including the entire area between the boundary lines of every way (including but not limited to roads, streets, alleys, highways, boulevards, bridges, tunnels, or similar thoroughfares), whether acquired by purchase, grant, or dedication and acceptance by the city or by the public, that has been opened to the use of the public for purposes of vehicular travel.

    Public way construction entity means the City of Houston, the Metropolitan Transit Authority of Harris County, Texas, the Texas Department of Transportation, Harris County, Harris County Flood Control District, or any other public entity performing or causing to be performed transportation improvement construction or construction-related activities in public ways.

    Traffic-control device means a traffic sign, signal, or marking that is placed and maintained in accordance with state law and this Code.

    Transportation improvement means the portion of work within the finished paved surface of a public way undertaken by or pursuant to contract for the state or a political subdivision of the state for the purpose of improving or maintaining public way transportation and related storm drainage and street lighting infrastructure, but does not include any activity, such as connection to other facilities, that cuts, penetrates, or bores under a public way other than the one being improved or maintained pursuant to the contract or that cuts, penetrates or bores under the public way after installation of new paving.

(Ord. No. 00-1115, § 2, 12-20-00; Ord. No. 01-203, § 2, 2-28-01; Ord. No. 06-595, § 2, 6-7-06; Ord. No. 2018-11 , § 50, 1-10-2018)